October 8, 2026
On September 29, 2026, six contractors submitted bids to six-lane Highway 25, the stretch of Lakeland Drive from Grants Ferry Road east to Highway 471. MDOT gave each one a choice. A contractor could promise to finish sooner, and MDOT would count every working day it gave back at $7,550 when comparing bids. All six bidders entered 424 working days, the maximum the contract allows.
If you're comparing homes in Flowood and along the Lakeland corridor toward the reservoir, that one detail matters more than any rendering of the finished road. The construction calendar is now set in public documents, and nobody competed to shorten it. You can read the next few years of this corridor on a calendar. The bid sheets give no reason to expect an early finish.
MDOT used A+C bidding on this job. "A" is the dollar cost of the work. "C" is the number of working days a contractor promises, multiplied by $7,550 a day. MDOT adds the two together only to rank the bids. The C value is never paid to the contractor, and any bid over 424 working days is rejected. In practice, a faster schedule is a discount a contractor can offer to win.
Here's how the unofficial checked results came out.
| Bidder | Bid amount (A) | A+C total | Implied C |
|---|---|---|---|
| Hemphill Construction Company, Inc., Florence | $57,151,644.00 | $60,352,844.00 | $3,201,200 |
| T. L. Wallace Construction, Inc., Columbia | $61,685,350.09 | $64,886,550.09 | $3,201,200 |
| Necaise Brothers Construction Co., Inc., Gulfport | $65,497,039.15 | $68,698,239.15 | $3,201,200 |
| Ste-Bil Grading Inc., Waterford | $68,595,694.90 | $71,796,894.90 | $3,201,200 |
| Joe McGee Construction Company, Inc., Lake | $71,213,566.40 | $74,414,766.40 | $3,201,200 |
| W. G. Yates & Sons Construction Company, Jackson | $76,708,752.90 | $79,909,952.90 | $3,201,200 |
Every bidder's C comes to $3,201,200, which is 424 days times $7,550. The difference between the bids came entirely from price. Hemphill's bid was about $4.5 million below the next one, and no one was willing to commit to a shorter schedule to close that gap.
As of October 5, 2026, MDOT's letting calendar shows the "As Read" and "Checked" results for the September 29 letting, but the "Bid Awards" column, which holds the official results, is still blank. Hemphill is the apparent low bidder until MDOT posts the award. The contract documents say MDOT expects to issue the Notice of Award by October 13, 2026.
A buyer looking at a home near Lakeland Drive this fall is looking at a road on a schedule MDOT has already published. These dates come straight from the bid package and MDOT's public statements:
When MDOT announced the funding in May, it said both this project and the I-55 widening in Madison County would take two to three years to build. The bids give no reason to expect less. A family that closes on a home along this corridor in spring 2027 will move in about when work begins.
A September 23 addendum sets two firm limits. The northbound lanes of Highway 25 can't be closed from 3 to 6 p.m., Monday through Friday. The southbound lanes can't be closed from 7 to 9 a.m., Monday through Friday. A contractor that misses either deadline is charged $500 for every full or partial five-minute period until the lanes reopen. When a bidder asked whether this applied to every stage of the work, MDOT said the restrictions apply "for all phases of the project."
That $500 per five minutes is real money, so the contractor has strong reason to keep those two windows open. The rule covers only those hours. Lane closures in other directions and at other times of day, plus weekend work, are all still allowed under the addendum.
If you're weighing two homes, think about when your household actually uses the road, beyond how far the home is from Lakeland. A commute that lines up with the protected windows will feel this project differently than midday errands or Saturday trips toward the reservoir.
The most specific rule in the package covers the east end of the project. The bid documents call it Milestone 1. The contractor must close Highway 471, rebuild the connection at Highway 25, and reopen it within 69 calendar days of the shutdown. That closure can happen only during the 2027 school summer break, and crews may work around the clock to finish it. Each day past the deadline costs the contractor $11,600.
Milestone 2 covers Spillway Road at Highway 471. It has a 60-day clock from shutdown and a penalty of $4,800 per day. The documents don't tie that closure to summer.
This is the work behind the "two roundabouts" from the May announcement. The final scope puts roundabouts on Highway 471 at the Highway 25 interchange ramps and at Spillway Road. It also adds ramp improvements and preservation work on the Highway 25 bridge over Plummer Slough. Pinelake Church's Reservoir campus sits at 6071 State Highway 25 with a Brandon address, at the end of the corridor where these closures happen.
For a buyer whose route runs through the Highway 471 interchange, summer 2027 is the one stretch to plan around. A home search that wraps up in spring 2027 could mean moving in just before or during that closure.
Michael Baker International designed the plans. The set includes typical sections for "signalized intersections" and for "J-turn intersections." At a J-turn intersection, drivers coming off a side street turn right and then make a U-turn a short distance down the highway. Direct left turns across traffic go away.
The plan set covers a 3.21-mile project. Its sheet index lists these side streets and entrances by name:
The index text doesn't say which of these get signals and which become J-turns. That's the question to settle for any specific home. A subdivision whose only way out is a side street on this list could gain a signal, or it could lose its direct left turn. The plan sheets themselves show the design, and the full plan set is public through MDOT's September 29 letting page.
The City of Flowood has been preparing too. Its board of aldermen approved a "Highway 25 Utility Relocation Claims Docket" at its October 6, 2025, meeting. The minutes don't give amounts, but the item shows the city was paying corridor utility claims a year before bids opened.
In one way this corridor is in better shape than it would have been two years ago. West Rankin Parkway opened in November 2025 after a $60 million build. The project had been in planning since 1992, and its final construction phase took about a year and a half. At the opening, MDOT Central District Commissioner Willie Simmons said the new road would take some traffic off Lakeland, Highway 25 and Interstate 20. Former Flowood Mayor Gary Rhoads put it more simply in WLBT's report: "Quality of Life is not sitting in a parked car."
For a buyer, that means the western end of Flowood already has an alternate route that didn't exist during earlier construction on Lakeland. Homes closer to Grants Ferry Road have more ways around the work zone. Homes farther east, toward Highway 471 and the reservoir, depend more on the corridor itself.
Nearly 20,000 drivers use this stretch of Highway 25 every day, according to MDOT. The state paid for the project by combining $150 million from House Bill 1938 with federal funds. MDOT Executive Director Brad White put it plainly in May: "It is an inconvenience. It's right in the middle of where everybody's trying to drive and carry out their life."
Not as of October 5, 2026. MDOT has posted checked bid results, which it labels unofficial, and the official award column for the September 29 letting is still empty. The contract documents expect the award by October 13, 2026.
Contract time begins March 10, 2027, unless the contractor asks to start earlier and MDOT agrees.
The contract ends when the allowed working days are used up, plus any extensions MDOT grants under its standard specifications. MDOT's public estimate is two to three years.
The plan set includes both signalized and J-turn designs. Check the plan sheets covering that specific street rather than assuming either way.
No. The closure at Highway 25 can happen only during the school district's 2027 summer break, and the contractor must reopen it within 69 calendar days of the shutdown.
If you're comparing homes along Lakeland Drive and want to know which intersection a property depends on and how its move-in date lines up with this construction calendar, call or text Renee for a local market consultation. Renee Grimes can go over the MDOT schedule with you before you write an offer.