November 5, 2026
Behind Topgolf on Colony Park Boulevard, crews are already doing dirt work for a 250-room hotel. The conference center that hotel is paired with is further back. On November 2, the Madison County Board of Supervisors had a proposed resolution on its agenda about hiring the center's architect, engineer and owner's representative. One project is putting up a building, and the other is still choosing who will design one.
The two are bound by one financing deal, which is why the order matters. Look at how Madison County plans to repay the conference center debt, and every layer of protection leads back to the hotel.
On September 8, supervisors voted 3-2 to issue $48 million in urban renewal revenue bonds. The money will buy 13 acres from PraCon MS Fund LLC and build a 50,000-square-foot conference center at Prado Vista, according to WLBT. The county is paying about $795,000 an acre for that land. Documents show the bonds being repaid over 20 years from the project's net operating revenue.
The City of Ridgeland's July 24 release sets out repayment in three layers:
Ridgeland Mayor Gene McGee explained the tourism rebate this way to WLBT in July:
"The tourism rebate is based on tax revenue that does not exist today because the project has not yet been built. Without this development, there is no conference center, no additional hotel guests, and no new tourism tax revenue to collect."
The Madison County Journal reported that Prado said he was also giving up a developer fee worth about $5 million to his company. Prado said the tourism rebates would be handed over across a 15-year period.
Look at those three layers side by side. The tourism rebate comes from visitors staying and spending at the development. Conference revenue depends on groups booking events, and those groups need somewhere nearby to sleep. The backstop is a lien on the hotel property itself. Prado says the hotel will be privately financed and will cost the county and the city nothing. Even so, the county's protection on its own bonds runs through that private building at almost every step.
Officials and supporters have said this from the start. Board President Gerald Steen called the deal a way to build a conference center without raising taxes. McGee said the people who benefit financially from the development should carry its cost instead of existing taxpayers, in the Mississippi Business Journal's October 2 coverage.
WLBT also reported that because the county issues the bonds, taxpayers could be on the line if the project doesn't bring in enough to cover the debt. McGee acknowledged that risk and said the structure was designed to keep it small. District 1 Supervisor Casey Brannon voted against the urban renewal plan in July. He told WLBT that debt service would run 15 to 20 years and would take money off the table that could otherwise go toward lowering taxes.
Both statements are part of the public record. The financing was built so that existing tax revenue isn't the planned source of repayment. Because the debt sits on the county's books, the hotel's success is what keeps that plan working.
The deal's final step explains why two supervisors kept pushing back. The Madison County Journal reported that once the conference center is paid off, ownership reverts to Prado for $10, and the title requires the building to remain a conference center for 20 years after that. Prado said the trade-off is that his company pays the interest on the bonds over 20 years and gives up the tourism rebates.
At the September 8 meeting, District 2 Supervisor Trey Baxter offered changes. WLBT recorded the outcomes:
Steen, District 4 Supervisor Karl Banks and District 5 Supervisor Paul Griffin voted for the final package, and Baxter and Brannon voted against it. Prado said ongoing oversight would come from a board of representatives from Ridgeland, the county and the Madison County Economic Development Authority. That board would receive budgets and financial reports, and project money would be held in controlling accounts.
The hotel and the conference center are moving at different speeds, and that gap is the most useful thing to understand about Prado Vista for the next couple of years.
| Date | What happened |
|---|---|
| Dec. 30, 2025 | Madison County Journal reports Topgolf Way, a new road east of Topgolf, built to serve future Prado Vista development |
| Feb. 2, 2026 | Supervisors' first conference center actions pass 4-1-1 |
| March 2026 | Ridgeland votes unanimously to support the urban renewal plan |
| July 20, 2026 | Supervisors approve the urban renewal plan 3-1 |
| Sept. 8, 2026 | Supervisors approve the $48 million bond plan 3-2 |
| Sept. 9, 2026 | Hotel dirt work underway, and Prado estimates completion within 13 months |
| Oct. 2, 2026 | Explore Ridgeland fielding booking inquiries as far out as 2028 |
| Nov. 2, 2026 | County agenda lists a proposed resolution on hiring the center's design professionals |
Prado's 13-month estimate came while hotel dirt work was already underway. The conference center was still at the stage of picking an architect and engineer in early November. McGee told the Mississippi Business Journal the project still has to get through design, construction and opening, and that leaders will have to manage construction costs and finish the drawings. Groups asking about 2028 dates fit a meeting hall that opens after the hotel beside it.
The hotel will be a Dolce by Wyndham, the first in Mississippi. Wyndham describes Dolce as its upper-upscale, resort-oriented meetings brand. Prado told supervisors Dolce would handle management.
Prado Vista is a 77-acre development at Colony Park Boulevard and Sunnybrook Road, just east of I-55. The parts you'd use most often come from private tenants, separate from the county bonds. Topgolf, the state's first, is already the anchor. Earlier this year the development announced a Dave & Buster's, an unnamed grocery store and four independent restaurants. Ridgeland also planned a traffic signal on Colony Park Boulevard near Topgolf and Ridgeland High School, tied to the new Topgolf Way entrance.
The public piece answers a long-standing local gap. McGee told the Business Journal there is nowhere in Ridgeland or Madison County to host an event of roughly 1,500 people under one roof. At the September meeting, Deborah Martin, incoming chair of the Madison County Business League and Foundation, pointed out that Madison Central, Germantown and Ridgeland High School hold their graduations at the coliseum in Hinds County. The new center is designed for up to 1,800 attendees.
For a buyer comparing Ridgeland with other towns around Jackson, here is the practical takeaway. Over the next year or so, the building rising behind Topgolf will most likely be the hotel. The county's financing plan leans on that hotel's success, and the conference center follows it on a slower timeline. Whatever happens on Colony Park Boulevard in the meantime depends on private tenants and city road work, which move on their own schedules.
Is the conference center funded by property taxes? City and county officials say the plan repays the bonds from project revenue and tourism rebates, with a lien on the hotel as the backstop. WLBT reported that the county still carries risk because it is the one issuing the bonds.
When does it open? As of the Mississippi Business Journal's October 2 report, design, construction and opening were all still ahead, and Explore Ridgeland was handling inquiries for dates as far out as 2028.
How many jobs are expected? Prado said the conference center and hotel will have 200 full-time and part-time jobs once both are finished.
This post is general information about a public financing deal, not tax or financial advice. Please check how county debt or taxes affect your own situation with a qualified professional.
If you're deciding where to buy around Colony Park Boulevard and want to talk through what's moving at Prado Vista and when, call or text Renee Grimes for a local market consultation.
Discover why buyers and sellers trust Renee Grimes for expert real estate guidance. With over 20 years of experience, she ensures a seamless, personalized experience.